Dispatch highlights some of the most important legal developments during the last month, relating to the building, engineering and energy sectors.
April's Dispatch looks at adjudication & “conclusive evidence” provisions, as well as making claims under UCTA.
Battersea Project Phase 2 Development Company Ltd v QFS Scaffolding Ltd [1]
What was the interplay between a “conclusive evidence” provision, and adjudication proceedings?
South East Water Ltd v Elster Water Metering Ltd [2]
What do you need to do to show that a term is unreasonable under the Unfair Contract Terms Act (UCTA)?
download (PDF 80K) April's Dispatch [3]
Adjudication [4] | Alternative Dispute Resolution [5] |
Arbitration & litigation [6] | Contract issues [7] |
Public procurement [8] | Other [9] |
Links
[1] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/archive/battersea-project-development-qfs-scaffolding
[2] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/archive/south-east-water-elster-water-metering
[3] https://www.fenwick-elliott.co.uk/sites/default/files/dispatch_issue_286.pdf
[4] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/adjudication
[5] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/alternative-dispute-resolution
[6] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/arbitration-litigation
[7] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/contract-issues
[8] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/public-procurement
[9] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/other
[10] https://www.fenwick-elliott.co.uk/research-insight/newsletters/dispatch/archive